  Shirdi airport ready for take offs from November

Shirdi airport ready for take offs from November

AGE CORRESPONDENT
Published : Sep 24, 2016, 1:45 am IST
Updated : Sep 24, 2016, 1:45 am IST

There’s good news for those planning to visit Shirdi in the next few months.

Deepak Sawant
 Deepak Sawant

There’s good news for those planning to visit Shirdi in the next few months. The Maharashtra Airport Development Company (MADC) has said that construction of the Shirdi airport is nearing completion and facility will be ready by the first week of November.

According to a top MADC official the work on Shirdi airport is in the final stages.

“The air traffic control (ATC) will be ready by the first week of November. It is set to be launched any time after November 1,” said Vishwas Patil, Managing Director of MADC.

He however, also said that though the work on the terminal building spread over 3,000 sq meter is in progress. It will be completed by November. Initially, the flight operations will be restricted between sunrise and sunset and the night landing facility will be installed by January 15, 2017. Once the flight operations start, devotees of from across the world will be able to fly to Shirdi (to visit the famous Saibaba shrine here).

Out of the total cost of Rs 325 crore, the MADC has spent Rs 230 crore so far on the airport.

“The airport crash tender imported from Austria at a cost of Rs 5 crore is ready. This ultra modern vehicle can reach any part of the airport within one and half minutes,” he said.

Maharashtra Chief Minister Devendra Fadanvis is keen on inviting Prime Minister Narendra Modi for the inauguration of the airport. In the next two years, a permanent terminal building and ATC tower would be built on 5,000 sq metre land.