Some light on Tangedco losses

Almost every thermal plant commissioned by Tangedco has seen a delay of 22 to 33 months

January 02, 2015 12:11 am | Updated 01:31 pm IST - CHENNAI

A view of North Chennai Thermal Plant in Chennai. Photo: B. Jothi Ramalingam

A view of North Chennai Thermal Plant in Chennai. Photo: B. Jothi Ramalingam

On December 12, 2005, the Tamil Nadu Electricity Board (TNEB) gave its approval for taking up the North Chennai Thermal Power Project Unit I (1x600MW). On March 20, 2014, that is, nearly a decade later, the unit was commissioned.

Critically, the time-gap between the scheduled date of commissioning to the actual date of commissioning was 33 months. Due to the delay, the generation loss in commissioning this unit alone was over 10,000 million units (MUs).

Similarly, the Comptroller and Auditor General of India (CAG) has calculated the generation loss due to delay in commissioning of the North Chennai Thermal Power Plant Unit II and Mettur Thermal Plant Stage III to be above 6,500 MUs each. The generation loss in these three units was over 22,500 MUs. For every unit lost, the Tangedco has to purchase power at a higher cost from private sources.

Almost every thermal plant that was commissioned by Tangedco, the State’s power utility in the past few years has seen a delay of 22 to 33 months. While the Vallur Unit I and II were also delayed by over two years, Vallur Unit III is yet to be commissioned. Initially, the Tangedco set August 2014 as deadline. Then Electricity Minister Natham R. Viswanathan assured that the plant would be commissioned in December.

Now the New Year has set in. Tangedco officials still have no answers about the delay and always downplay it, stating that it was not in their hands. “Once, the boiler that was being brought was washed away in floods. These things happen,” says a senior Tangedco official.

In his dissent order (on the power tariff hike), Tamil Nadu Electricity Regulatory Commission member S. Nagalsamy has mentioned about the ‘inordinate delays” in commissioning of new thermal plants.

When the issue was raised by public in their written petitions, the Tangedco replied that it would recover Liquidated Damages (LD) from EPC contractors. They also confirmed that they have retention amount to recover the LD.

The fact remains that if the LD and compensation are recovered, this will either reduce the capital cost of the projects. With this huge revenue, the increase in tariff would not be required, Mr. Nagalsamy contended.

Thermal Plant Scheduled Date of commissioning Date of commercial operations
Vallur Unit IOctober 2010November 2012
Vallur Unit IIMarch 2011August 2013
Vallur Unit IIISeptember 2012Yet to be commissioned
NCTPP Unit IMay 2011March 2014
NCTPP Unit IINovember 2011May 2014
MTPPSeptember 2011October 2013

Tangedco higher officials are unwilling to talk about the LD recovered for the recently commissioned thermal units. “It is all in the contract but it is between Tangedco and the contractor. It is not for public knowledge. As per the terms, we recover the LD, once the contract is over,” says a senior official.

Obviously, the LD runs into several thousand crores. The CAG report throws light on this aspect. While the (gross) contract value of the North Chennai Thermal Power Plant Unit I&II and the Mettur Stage III is Rs 7,764 crore, the LD/penalty leviable for the delays works out to Rs 7,418 crore. That is, the LD for delays is almost the value of the contract itself.

Policy-makers are quite surprised. “There has to be a cap. Otherwise, no contractor will take up the work,” says a policy-maker. Tangedco officials, again, refuse to reveal the cap for the above mentioned plants.

However, an affidavit submitted by the Tangedco before the TNERC reveals that the cap for the North Chennai plants is 10 per cent of the contract value of the projects. While the LD works out to almost the contract value, the Tangedco at best can recover only 10 per cent.

For instance, the (gross) contract value of the North Chennai Unit I was Rs 2,475 crore. The LD/penalty leviable was Rs 2,650 crore. Actually the Tangedco can recover only Rs 265 crore.

Whichever way you look at it, the Tangedco is suffering huge losses, running into thousands of crores, due to delay in commissioning of thermal plants. It is the public who end up paying for its inefficiency.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.