Wesizwe reaches underground milestone
Bakubung mine manager Eddie Mohlabi discusses the gains made by the platinum mine during the last stretch of 2014. Date recorded:11.12.14. Camerawork and video editing: Nicholas Boyd.
Photo by Duane Daws
Photo by Duane Daws
RUSTENBURG (miningweekly.com) – Chinese-backed emerging platinum producer Wesizwe Platinum has reached another milestone at its flagship Bakubung platinum mine project, which is already two-and-a-half years ahead of schedule.
Despite facing tensions in the platinum belt during the year, continual progress had been made in sinking the main and ventilation shafts at Wesizwe’s platinum mine project, with the intersection of the Merensky reef a mere 11 m away from the current level of the main shaft.
All eyes were now on the intersection of the secondary upper group two (UG2) reef, which would be reached shortly, Bakubung mine manager Eddie Mohlabi said during an underground site visit on Thursday.
Bakubung’s most recent milestone earlier this year was the cutting of the first level of the ventilation shaft, some 690 m below the shaft level and 45 m above the first intersection of the platinum-rich Merensky reef.
The main shaft of the envisaged 420 000 ounce-a-year 4E (platinum at 62.4%, rhodium accounting for 7.4%, palladium at 28% and gold at 2.2%) platinum group of metals underground mine was now at 730 m below collar and the ventilation shaft 750 m below collar.
The development of its main shaft to 970 m, which would have a hoisting capacity of 255 000 t of ore and 15 000 t of waste a month, would be completed by October next year, 55 days ahead of schedule.
An initial 230 000 t/m would be mined from the Merensky reef, with the balance sourced from the UG2 reef. Once Merensky reef was depleted in the next 10 to 15 years, the full 255 000 t would be sourced from the UG2 reef only.
The ventilation shaft, which would reach its final depth of 880 m in September 2016, was 144 days ahead of schedule.
The implementation of an adopted optimisation plan earlier this year ensured that the mine, boasting a 30-year life-of-mine, would undergo its main commissioning in the fourth quarter of 2018, before being ramped up to full production in 2020.
Several services projects were on track, with the first phase of 20 MVA power supply from State-owned power utility Eskom commissioned during 2014, along with the signing of a bulk water-supply agreement with Magalies Water.
The group also concluded the housing project prefeasibility study, with focus now shifting to securing land in partnership with local communities for the development of housing.
A feasibility study had also kicked off on the first phase of the housing project, which would consider off balance sheet funding options.
Bakubung would also shortly start construction of the access roads for the mine.
During 2015, Bakubung would start its waste development programme, commission the bulk water supply, start Phase 2 of the power supply project and embark on key shaft bank installations.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation